The $150K Recovery

I joined a $150,000 Salesforce implementation three weeks behind schedule, with two weeks until a hard year-end deadline and only two developers available over the winter break. I cleared the requirements bottleneck, reset priorities with the client, and moved about 130 of 200+ workflows into production before year-end, within budget. The client re-signed their support contract and brought us additional projects.

The scope

At a glance

My role
Project Manager & Client Success Lead (sole PM), QuantumRhino
Client
Large national personal injury law firm
Project
Rebuild of 200+ legacy Salesforce workflows in custom Apex code (Salesforce's programming language) before the old format was retired
Value
$150,000 implementation
Method
Agile
Team
Me plus two developers (reduced crew over the company-wide winter break)
Stakeholders
Client executives, client IT, system users, developers
Starting point
About three weeks behind, key client inputs still missing, two weeks to the deadline
Outcome
About 130 of 200+ workflows live before year-end; the rest after the new year; on budget; support contract renewed and new projects won

The situation

The client's legacy Salesforce workflows were built in a format being retired, so they had to be rebuilt in custom Apex code before year-end. There was no room to move the deadline.

I joined the project two weeks before the end of the year. It was already about three weeks behind, and with the company-wide winter break, only two developers could work on it. I was the only project manager. Everyone was frustrated: the client's executives, their IT team, the people who used the system every day, and our own developers.

What I found

The developers weren't the problem. The client had never supplied information the build depended on, and the earlier tracking and communication let that gap go unnoticed. The team was waiting on answers nobody was chasing.

That changed the job. With 200+ workflows, two developers and two weeks, finishing everything wasn't realistic, and pushing the developers harder wouldn't close a requirements gap. I needed the client's answers fast, a shared decision on what mattered most, and every remaining hour spent on that work.

The recovery plan

  1. Made answering easy. I built a simple, easy-answer requirements template so the client could fill the gaps without decoding technical questions. We also asked them to survey every user to learn which functionality mattered most. The template came back within 24 hours, but only three or four users were surveyed. Instead of waiting for a perfect answer, we prioritized with the input we had and kept moving.
  2. Reset priorities with the client. In a reprioritization meeting, we agreed which workflows were business-critical for launch and which could follow after the new year.
  3. Aligned the developers on release order. With two developers, release order was everything. The team built against the agreed list, so every remaining hour went to workflows that had to launch.
  4. Communicated twice a day. Every day started with an opening update and ended with a closing update, with decisions and blockers in between. Nobody had to wonder where things stood.
  5. Made escalation paths explicit. When a decision or blocker came up, everyone knew who owned it and how fast it needed an answer.
RiskWarning signMy response
RequirementsClient inputs still missingEasy-answer template plus a working session to close the gaps
Schedule & capacityThree weeks behind, holiday capacity shrinkingReprioritized to critical workflows, set release order, made escalation paths explicit
User impactQuality-of-life updates had to wait until after launchKept deferred work visible, built workaround job aids, offered hands-on support

The tradeoff

We couldn't deliver all 200+ workflows by year-end, so I made that clear early instead of letting it surprise anyone at the deadline. We protected the workflows the business couldn't run without and moved the remaining functionality to after the new year, when the full team was back.

Deferring work only builds trust if people can see it's coming. The deferred items stayed on the visible plan, I built workaround job aids for users, and I offered hands-on help so day-to-day work wasn't disrupted while those updates waited.

The result

About 130 of the 200+ workflows were promoted to production before the year-end deadline, covering the business-critical core. The remaining functionality went live after the team returned from the break, and users had job aids and support in the meantime. The project stayed within its $150,000 budget.

The relationship recovered too. The client sent a heartfelt thank-you, re-signed their expiring support contract, and brought us additional projects.

What this shows

  • I diagnose before I push. The fix was a requirements gap, not a velocity problem. Treating it as a velocity problem would have burned out a two-person team without moving the date.
  • I decide with the information available. When the user survey came back thin, we prioritized with what we had instead of stalling.
  • I make tradeoffs visible early. Clients can handle a hard choice. What hurts trust is a surprise at the deadline.
  • I translate between business and technical teams. The template turned developer questions into answers a law firm could give within a day.
  • I protect the people downstream. Deferred work came with job aids and hands-on support, so users weren't left waiting without help.
Rebuilt and sanitized: illustrative.

Sample artifact: the easy-answer requirements template

Rebuilt from memory and sanitized. Workflow names and answers are illustrative.

The template replaced open-ended technical questions with choices a busy client could answer in minutes. The developers got what they needed, and the client didn't have to learn our vocabulary.

Part 1: For each workflow, tell us how it's used

WorkflowWhat happens today, in plain wordsWho uses itHow oftenNeeded on day one?Anything that must not change?
New case intakeCreates a case and assigns an attorney when a new client signsIntake teamDailyYes / Can wait
Medical records requestSends a records request and sets a follow-up reminderCase managersDailyYes / Can wait
Settlement noticeNotifies accounting when a settlement is recordedAttorneys, accountingWeeklyYes / Can wait
Status update emailEmails the client when the case stage changesAutomaticAs neededYes / Can wait

Part 2: Quick questions (circle one)

  1. If this workflow stopped working for a week, what would happen? Work stops / We'd manage manually / Little impact
  2. Does anyone outside your firm see the result of this workflow? Yes / No
  3. Who can confirm the answer if we have a follow-up question? Name and best way to reach them

Part 3: Two-minute user survey (send to every system user)

  1. Which three tasks in the system do you do most often?
  2. Which one task would hurt most if it broke?
  3. What's one thing that annoys you about the current system?
Rebuilt and sanitized: illustrative.

Sample artifact: the daily updates

Rebuilt from memory and sanitized. Dates and counts are illustrative.

Every day opened and closed with a short update to client executives, client IT and the developers. Same format every time, so anyone could scan it in 30 seconds.